Under Construction Projects of Lines and Substations in Yangon Division

No

Name of Project 

Substation MVA Location
1

230kV Wartayar –( Ywarma – Hlaingtharyar) -

Line (8) Miles & Wartayar Substation 

Wartayar Substation Switchbay

Yangon Division, Shwe Pyi Thar

Township, Htantabin Township

2

230kV Wartayar – Hlawga Line (10 Miles) &

Switchbay Extension

Wartayar

Hlawga 

Switchbay

Switchbay

Yangon Division,Shwe Pyi Thar

Township & Mingalardon Township 

3

230kV Khanaungto Substation

Khanaungto Switchbay

 Yangon Division,

Sategyikhanaungto Township 

 230kV Wartayar–( Ywarma – Hlaingtharyar) - Line (8.04) Miles & Wartayar Substation

1.     Location                -   Yangon Division,

                                           Shwe Pyi Thar Township, Htantabin Township

2.     Scope of Work         

                       (A)         Line                             -     (8.04)Miles, (40)Towers

                       (B)         Substation                   -     230kV Switch Bay (2) Bay

3.     Situation of Signing  Contract                  -     Project Balance Material

                                                                                    Project Manager(1)+(Civil) Southen      

4.     Starting Date of Project (Effective Date)   -     (1.2.2018)       

5.     Ending Date of Project (Approximation)   -     February, 2022

6.     Complete Situation                                      -     Line      -  ( 99 % )

                                                                    -     Stringing Work at T3 toT13 (100%)

                                                                                     Substation-  ( 100 % )

(1) 230kV Wartayar – Hlawga Line (9.3 Miles) & Switchbay Extension

1.     Location                -   Yangon Division, Shwe Pyi Thar Township & Mingalardon Township

2.     Scope of Work      

                       (A)         Substation                        

                                    230kV Switch Bay ( Wartayar Substation ) -         (2) Bays

                                    230kV Switch Bay (Hlawga Substation )    -        (2) Bays  

                       (B)         Line

                                    230kV Line                                                   -        (10) Miles

3.     Situation of Signing  Contract                       

              Contract No. & Date (Material)                   -        38/DPTSC(PTP)/2019-2020 (3.6.2020)

              Contractor                                                  -         Khin Maung Nyunt Trading Co., Ltd.

              Contract No. & Date (Foundation,Erection) -        78/DPTSC(PTP)/2020-2021 (7.10.2021)

              Contractor                                                    -      Zeya & Associates Co., Ltd.

                                                                                          Project Manager(1)+(Civil) Southen

4.     Starting Date of Project (Effective Date)         -    (7.10.2021)       

5.     Ending Date of Project (Approximation)         -    (6.10.2023)

6.     Complete Situation        -        Excavation -  20% 

                                                          Foundation-  20%

                                                            Erection -  0%

(2)230kV Khayan (Thonegwa) – (Thanlynn-Kamarnad) Line In/Out (2)Miles & Substation

1.     Location                                                       -   Yangon Division, Khayan Township & Thonegwa

2.     Scope of Work          

       (A) Substation

                      230kV Line Bay                               -    (4) Bays

                      230kV Bus Coupler                          -    (1) Bay

                      230kV Transformer Bay                   -    (2) Bays

                      230kV Measuring Bay                      -    (2) Bays

                      230kV Single Phase Transformer     -    (6) Nos

                      33kV Line Bay                                  -    (10) Bays

                      33kV Transformer Bay                     -    (2) Bays

                      33kV Measuring Bay                        -    (2) Bays

                      33kV Bus Section Bay                      -    (1) Bay     

                      E-Type                                              -    (1) No

       (B) Line

                      230kV Line In / Out                            -    (2) Miles

3.     Situation of Signing  Contract                      

                      Contract No. & Date (Material)         -    87/DPTSC(PTP)/2019-2020 (15.6.2020)

                      Contractor                                         -    Zeya & Associates Co., Ltd.

                      Contract No. & Date                         -    77/DPTSC(PTP)/2020-2021 (24.9.2021)

                                                                                    (Switchyard Foundation & E-Type Building)

                      Contractor                                             -    AhtinkayaCo., Ltd.

                                                                                         Project Manager(1)+(Civil) Southen

4.     Starting Date of Project (Effective Date)         -    (24.9.2021)

                                                                                         (Switchyard Foundation & E-Type Building)

5.     Ending Date of Project (Approximation)          -    (23.9.2023)

                                                                                          (Switchyard Foundation & E-Type Building)

6.     Complete Situation   -    Substation                   -    Control Building(100%) , Fencing(100%),

                                                                                          Switchyard Foundation (92.73%), E-Type (100%)   

                                                                                          All Total (78.8%)                                                                                                                                                      

(3) 230kV Khanaungto Substation

1.     Location                                                     -   Yangon Division, Sategyikhanaungto Township

2.     Scope of Work      

                                    Fence of Substation         -  (2510)ft Brickfence and Main Gate Door

                                                                                 (6620)ft Barbed Fence

3.     Situation of Signing  Contract                       

                                   Contract No. & Date        -  81/DPTSC(PTP)/2020-2021

                                   Contractor                       -   Power Heaven (28.9.2023)

4.     Starting Date of Project (Effective Date) -    (29.9.2021)     

5.     Ending Date of Project (Approximation) -    (28.9.2023)

6.     Complete Situation                                   -    Fence of Substation – (87.18%)

                      

230 kV Khanaung To Substation (Fence)

Brick Fencing Work

 (4) 230kV Hlawga – East Dagon Line (13)Miles & 230kV Switch Bay Extension at Hlawga Substation

1.     Location                                                        - Yangon Division, East Dagon Township, Mingalardon Township

2.     Scope of Work      

                      (A)         Line                                     - (13)Miles             

                      (B)         Substation                           -  230kV Switch Bay (Hlawga )(2) Bay

၃။    Situation of Signing  Contract                      

            Contact No. & Date (Material)                     -  86/DPTSC(PTP)/2019-2020(15.6.2020)

            Contractor                                                   -   Zeya & Associates Co., Ltd.

            Contact No. & Date (Foundation,Erection) -   80/DPTSC(PTP)/2020-2021 (24.9.2021)

            Contractor                                                   -   IGE Power Co., Ltd.

                                                                                    Project Manager(1)+(Civil) Southen

4.     Starting Date of Project (Effective Date)     -  (24.9.2021)  

5.     Ending Date of Project (Approximation)    -  (23.9.2023)

6.     Complete Situation                                       -   

 

(5) 500kV Pharyargyi - Hlaingtharyar Line ( 56.8 )Mile

1.     Location                                                      - Bago Division , Yangon Division

2.     Scope of Work                                               Line  - (T-55) to ( T- 149)(Survey approved ) ( In Yangon Division)                                                                   

3.    Situation of Signing   Contract                      

                      Contract No. & Date                       - 3/ DPTSC (PTP) /2019-2020 (18.12.2019)

                      Contractor                                      -  Mitsubishi  Coporation Co., Ltd

4.     Starting Date of Project  (Effective Date) - (16.1.2020)    

5.     Ending Date of Project (Approximation)  - (15.7.2022)

6.     Complete Situation                                    -  Excavation -  (16) Nos  Finished                                                                                                                                                                                           - Foundation- (14) Nos Finished                                                                                                                                                                                               - Erection -  0%

 

(6) 500kV Hlaingtharyar Substation

1.     Location                                                       -  Yangon Division , Hlaingtharyar  Township

2.     Scope of Work                                            -   500/230/33 KV , 2 x     500MVA  Substation     

3.     Situation of Signing  Contract                           

                      Contract No. & Date                       -   91/DPTSC(PTP)/2019-2020 (16.6.2020)

                      Contractor                                       -   Sojitz Corporation

4.     Starting Date of Project  (Effective Date) -   ( 16 . 6 . 2020 )      

5.     Ending Date of Project (Approximation)  -   ( 15 . 6 . 2023 )

6.     Complete Situation                                    -    Finished Sand Filling and Road         

                                                                                  Embankment  for Switchyard – 63.35%

      

 (7) 230kV Pharyargyi – ( Kamanat - Myaungtagar )Line ( 8.7 )Mile

1.     Location                                                      -  Bago Division , Yangon Division

2.     Scope of Work                                               Line  - (T-69) to ( T- 109) ( In Yangon Division)

 3.    Situation of Signing    Contract                      

                      Contract No. & Date                       -  10/DPTSC(PTP)/2021-2022 (9.3.2022)

                      Contractor                                      -   (Consortium of Kanaung Co.,Ltd and

                                                                                 Integral Power Transmission Group Co.,Ltd)

4.     Starting Date of Project  (Effective Date) -  (9.3.2022)

5.     Ending Date of Project (Approximation)  -  (8.3.2024)

6.     Complete Situation                                    -