Bago Division


230kV Saparkywei - Taungoo Transmission Line (9.5) miles and

230kV Taungoo Substation (2) Bays Extension

1.  Location                                                      -  Bago Division , (Taungoo Township , Oktwin Township)

2.  Scope of Work           

          (A)  Line                                                  -   (9.5) miles

          (B)  Substation                                        -   230kV Switch Bay (2)Bays

3.  Situation of Signing Contract

          (A) Line

               Construction                                       -  Project Manager (2) Office, Tharyargone (PTP)

               Contract No. & Date(Materials)         -   59/ DPTSC(PTP)/2019-2020 (3.6.2020)

               Contractor                                          -  Khin Maung Nyunt Co.,Ltd

          (B) Substation

              Construction                                      -   Project Manager (2) Office, Tharyargone (PTP) & Project Manager (Civil) Southen

              Contract No. & Date(Materials)         -   83/ DPTSC(PTP)/2019-2020 (28.4.2020)

               Contractor                                        -   Aye Chan Mon Co.,Ltd

4.  Starting Date of Project (Effective date) -  Line              -       (1.2.2020)

                                                                           Substation    -       (20.12.2020)

5.  Ending Date of Project (Approximation) -  Line              -       March, 2022

                                                                           Substation    -       November,2021

6.  Complete Situation                                    -  Line             -       (99.86%)      

                                                                            Substation    -       (100%)

230kV Saparkywei - Taungoo Transmission Line (9.5) miles

230kV Taungoo Substation (2) Bays Extension

 

500kV Kankaung (Meiktila) – Saparkywei(Taungoo) Transmission Line Part II (72.51) miles and 500kV Saparkywei Substation

 

1.  Location                                                                  -   Nay Pyi Taw (Ottarathiri Township,Dekkhina Thiri Township ,

                                                                                          Lewe Township) Bago Division  (Taungoo Township , Yedashe Township)  

2.  Scope of Work                   

          (A)  Line                                                              -   (72.51) miles

          (B)  Substation                                                   -    500/230/33kV (500MVA) x 1banks Tr

                                                                                          500/230/33kV 100MVAR Shunt Reactor ( 4 Unit)

  3.  Situation of Signing Contract

          (A)  Line

                Contract No. & Date(Stringing)                      -   3/DPTSC(PTP)/2018-2019 (26.12.2018)

               Contractor                                                       -   SEPCO Co.,Ltd

               Contract No. & Date(Foundation & Erection)  -   295/DPTSC(PTP)/2013-2014(25.1.2018)

               Contractor                                                        -   Dragon Emperor Co.,Ltd

                Contract No. & Date(Foundation & Erection) -   296/DPTSC(PTP)/2013-2014(16.7.2015)

               Contractor                                                       -   Minanawrathar Co.,Ltd

               Contract No. & Date(Foundation & Erection)  -   297/DPTSC(PTP)/2013-2014(14.7.2015)

               Contractor                                                       -   Chan Hein Co.,Ltd

               Contract No. & Date(Foundation & Erection)  -   298/DPTSC(PTP)/2013-2014(25.1.2018)

               Contractor                                                       -   Khin Maung Nyut Co.,Ltd

                Contract No. & Date(Instruction Service)      -   28/DPTSC(PTP)/2018-2019 (14.2.2019)

               Contractor                                                      -   KEPCO Co.,Ltd

                Contract No. & Date(Supply of ACSR)         -   37/DPTSC(PTP)/2018-2019 (11.3.2019)                                                                   

                  Contractor                                                   -   Zeya & Associates Co.,Ltd

            (B)   Substation                                                          

                Contract No. & Date                                     -   57/DPTSC(PTP)/2019-2020 (6.3.2020)

               Contractor                                                     -   Marubeni Corporation

4.  Starting Date of Project (Effective date)             -   Line             -    (26.12.18)

                                                                                         Substation  -   6.3.2020

5.  Ending Date of Project (Approximation)            -   Line            -   October, 2023   

                                                                                         Substation  -  September,2022

6.  Complete Situation                                               -  Line            -     94.34 %

                                                                                         Substation  -    24.19 % (Civil Work)

500kV Kankaung (Meiktila) – Saparkywei(Taungoo) Transmission Line (72.51) miles

              500kV Saparkywei Substation

 

500kV Taungoo-Pharyargyi (Kamanat) Transmission Line (108.34)Miles and Substation

1.  Location                                                    -  Bago Division , (Taungoo Township , Oktwin Township , Phyu Township ,

                                                                            Kyauktagar Township , Daik-U Township , Bago Township )

2.  Scope of Work       

     (A) Line                                                      -   (108.34) miles

     (B) Substation                                            -     -

3.  Situation of Signing Contract

     (A) Contract No. & Date                            -   56/DPTSC(PTP)/2018-2019 (25.6.2019)

          Contractor                                            -   Doosan Engineering & Construction Co.,Ltd

      (B)  Substation                                                                 

          Contract No. & Date                             -    3/DPTSC(PTP)/2019-2020(Sojitz)

          Contractor                                            -    (Sojitz Co.,Ltd)

4.  Starting Date of Project(Effective date) -    (25.6.2019)

5.  Ending Date of Project (Approximation) -   June, 2022

6.  Complete Situation                                    -  Line          - (85.35%)

                                                                         -  Substation - (10.3%) (Civil Work)

500kV Toungoo-Pharyargyi (Kamanat) Transmission Line (108.34)Miles    

Pharyargyi Substation

 500kV Phayargyi – Hlaing Tharyar Transmission Line (14) miles

1.  Location                                                     -  Bago Division , (Bago Township)

2.  Scope of Work           

          (A)  Line                                                 -  (14) miles

          (B)  Substation                                       -     -

3.  Situation of Signing Contract 

          (A) Line                

         Contract No. & Date                       -  3/DPTSC(PTP)/2019-2020 (18.12.2019)

                 Contractor                                       -   Mitsubishi Coporation

          (B) Substation    Construction               -     

               Contract No. & Date(Materials)        -     

                Contractor                                        -                               

4.  Starting Date of Project (Effective date) -   Line          - (16.1.2020)

                                                                            Substation -  

5.  Ending Date of Project (Approximation) -  Line           -  (15.7.2022)

                                                                             Substation -      

6.  Complete Situation                                    -  Line            -   (54.86%)      

                                                                             Substation    -     

500kV Phayargyi – Hlaing Tharyar Transmission Line

 

230kV Phayargyi(Kamarnat)-Myaungtagar Transmission Line (23)miles

1.  Location                                                     -   Bago Division , (Bago Township )၊ Yangon Division , Hlaing Tharyar Township

2.  Scope of Work           

          (A)  Line                                                  -   (23) miles

          (B)  Substation                                        -        -

3.  Situation of Signing Contract

          (A) Line

               Contract No. & Date(Materials)         -  10/DPTSC(PTP)/2021-2022 (9.3.2022)

               Contractor                                         -  The Consortium of  Kanaung  & Integral Power Transmission Group Co,Ltd

          (B) Substation

                Construction                                     - 

               Contract No. & Date(Materials)         - 

                   Contractor                                     - 

4.  Starting Date of Project (Effective date) -  Line              -   (9.3.2022)

                                                                            Substation    -   

5.  Ending Date of Project (Approximation) - Line               -       (9.3.2024)

                                                                            Substation    -       -

6.  Complete Situation                                   -  Line              -       (12.61%)      

                                                                            Substation    -       -

230kV Phayargyi(Kamarnat)-Myaungtagar Transmission Line (23)miles

230/66/11kV, (150) MVA Kamarnut Substation (Extension)

1.  Location                                                     -   Bago Division (Front), Kamarnut Village

2.  Scope of Work           

          Substation                                                             

             230kV Incoming Bay                           -  4 Bays

             230kV Transformer Bay                      -  1 Bay

             230kV Bus Coupler Bay                     -  1 Bay

             230kV Measuring Bay                         -  2 Bays

             66kV Incoming/Main                           -   1 Bay

             66kV Outgoing Bay                             -   5 Bays

             66kV Measuring Bay                           -   1 Bay

3.  Situation of Signing Contract

          Contract No.&Date(Construction)           -   Project Manager(3)+(Civil) Southen

          Contract No.& Date(Materials)               -   73(T)/ESE/2019-2020 (4.2.2020)

          Contractor(Materials)                             -   Zillion Luck Engineering Co.,Ltd               

          Contractor(Transformer)                        -   KhinMaungNyuntCo.,Ltd

4.  Starting Date of Project (Effective date) -   (15.1.2021)     

5.  Ending Date of Project (Approximation) -   (31.10.2022)

6.  Complete Situation                                

          Switchyard foundation (Civil Work)        -   (98.8%)

          Substation (Installation)                         -   (72.11 %)

      230/66/11kV, (150) MVA Kamarnut Substation (Extension)

 

(A) 230kV Minhla – Athoke Transmission Line (101) miles and Minha &

Athoke Substations Extension

1.  Location                                             :-  Bago and Ayeyarwaddy Region

2.  Scope of Work                                    -     

     (A) Line                                                -   101 miles

     (B) Substation                                    -                                 

                                                                 -   230kV Switch Bay (3) Nos.Extension at Minhla Substation

                                                                 -   230kV Switch Bay (2) Nos. Extension at Athoke Substation

3.  Situation of Signing Contract

          Line/ Substation

          Construction                                  -    Khin Maung Nyunt TradingCo.,Ltd. and TBEA   Co.,Ltd.                                                                

           Contract No.& Date(Materials)     -    95/DPTSC (PTP)/2019-2020 dated 09.07.2020

           Contractor                                    -    Consortium of Khin Maung Nyunt Trading Co.,Ltd. and TBEA Co.,Ltd.

 4.  Contract Effective Date of Project  -     10.08.2020

5.  Completion Date of Project              -      09.08.2023 

      (Approximation)    

6.  Complete Situation

           Transmission Line                         -    0 % (Finalized Line Route, Tower  Type F approved)

           Substation                                     -    0 %

(B) 230kV Minhla Switchyard foundation & Fence

1.  Location                                             - :  Bago Region.

2.  Scope of Work                                   -           

                                                                 -   230/66 kV Transformer Plinth   Foundation

                                                                 -   66 kV Switchyard Bay Extension outgoing bay, bus bay, measuring bay, outgoing feeder (3) bays

3.  Situation of Signing Contract

          Substation

                Construction                             -   Power Heaven Co.,Ltd

                Contract No.& Date(Materials) -   81/DPTSC(PTP)/2020-2021 (29.9.2021)

                Contractor                                -    Power Heaven Co.,Ltd

4.  Contract Effective Date of Project  -   10/2021

5.  Completion Date of Project             -    9/2023

               (Approximation)   

6.  Complete Situation

                             Substation                   -   71% 

(Completion of Work )                                

 (Have Concreted Foundation to 66kV Gantry Foundation(6)Nos , 230kV  Gantry Foundation (1)Nos & 66kV DSE Foundation(3)sets, GCB Foundation(3)sets, CT Foundation(2)sets, LA Foundation(3) sets, DS Foundation(4)sets)  (Cable  Duct  making , 66kV  &  230kV Switch Bay Foundation  Iron manufacturing  Operations)                                          

            230KV MinHla Substation (66kV LA,DSE & CT Concrete Casting  Work , 66kV GCB & DS Concrete Casting Work)